Is a 40–60 TPH Small Asphalt Mixing Plant Enough for 50,000 m² Municipal Road Paving?

  • aimixglobal5
  • 3 days ago
  • 4 min read

When many municipal contractors in Indonesia plan a 50,000 m² road paving job, they often look at small asphalt plant options first. I understand that they want lower investment, simple mobility, and faster setup. Because of that, the question becomes very clear: Is a 40–60 tph small asphalt plant for sale enough for continuous municipal road construction? To answer it well, I look at the real asphalt demand, daily paving rhythm, plant capacity, and onsite logistics. With these points connected logically, you can judge whether the 40–60 tph range fits your schedule or if you need something bigger.

ALYQ Series mobile asphalt mixing plant for sale mini type

Understanding The Real Asphalt Demand For 50,000 m² Road Paving

Before I recommend any capacity, I calculate the required asphalt tonnage. The numbers show what the plant must deliver. For municipal roads, the asphalt layer usually falls between 5–7 cm. If I take 5 cm as a typical value, the asphalt consumption per square meter often stays around 110–130 kg. Because of this, paving 50,000 m² normally needs 5,500–6,500 tons of finished asphalt mix. Once we know this range, we can calculate how long a 40–60 tph aspal mixing plant mini will need to complete the project.

How Many Days Does a 40 TPH Plant Need?

A 40 tph plant can produce about 320 tons in 8 hours. If you run it for 10 hours, you get around 400 tons. That means the entire 5,500–6,500 ton job will take 14–18 days of production. This timeline might suit small contractors. But for municipal road authorities, they often want a shorter paving window to reduce traffic disturbance.

How Many Days Does a 60 TPH Plant Need?

A 60 tph plant gives about 480 tons in 8 hours or 600 tons in 10 hours. So the full asphalt demand takes 10–12 days. The faster cycle provides more project control. And because many municipal roads require phased construction, the 60 tph option balances speed with moderate investment.

ALT seires Drum mix asphalt plant for sale

Matching Plant Capacity With Daily Paving Output

Now that we know the asphalt demand, I shift the angle to paving speed. This part is important because your asphalt plant must keep up with the paver. If the paver moves faster than your production, you will stop too often. But if the plant produces far more than you need, you waste money. So I compare typical paving output with the 40–60 tph capacity to see if they match.

Daily Paving Output For Municipal Roads

A normal paving crew with a 6–8 m paver usually completes 2,500–3,500 m² per day. At 5 cm thickness, this equals 275–450 tons of asphalt. When I compare this with the production data above, both 40 tph and 60 tph plants can meet this daily requirement, but with different levels of flexibility.

Where 40 TPH Works Well

A 40 tph mini hot mix plant fits contractors who pave no more than 2,500–3,000 m² per day. It suits:

  • Small municipal roads

  • Village roads

  • Patch work or multiple small segments

  • Projects with lower daily targets

Since many small municipal jobs do not push high daily output, a 40 tph plant keeps cost low while completing the project on time.

Where 60 TPH Performs Better

A 60 tph plant supports larger work zones and longer daily paving hours. It suits:

  • Continuous municipal roads with 500–1,000 m stretches

  • Urban arterial upgrades

  • Contractors with strict project deadlines

  • Contractors who mix for both paving and commercial sales

Because of its higher output, the 60 tph plant leaves more buffer room if your paving rhythm increases due to better weather, extra rollers, or a faster paver.

ALYJ Series compact type mobile mini asphalt plant for sale

The Influence Of Logistics, Hauling Distance, and Operating Hours

Choosing plant capacity is not only about daily tonnage. I also consider hauling distance and working hours. They create real constraints for many Indonesian projects. Therefore, even if a 40 tph plant can theoretically meet the demand, your real performance depends on the combination of transport and jobsite scheduling.

Hauling Distance

The longer the haul, the more trucks you need. Asphalt cools fast. So if your trucks need 30–50 minutes to reach the site, you cannot risk low production. This is why contractors with long-distance hauling often select 60 tph instead of 40 tph. The higher capacity reduces waiting time and keeps asphalt temperature stable.

Operating Hours

Some municipal projects only allow daytime paving. When your operating window is short, you need more tons per hour. That makes the 60 tph plant a safer choice. But if your project lets you run day and night, the 40 tph plant becomes enough because you spread production across longer time.

ALT Series mini stationary asphalt drum mixing plant for sale

Comparing Cost and Result: Which One Brings Better Value?

Cost is always part of the decision. Many clients want to choose the lowest investment first. But I also look at the total project cost and not only equipment price. If a too-small plant delays the project by 5–7 more days, your labor and truck cost will rise. In contrast, a slightly larger plant may increase plant cost but reduce total project spending.

When 40–60 TPH Brings the Best Efficiency

For a 50,000 m² municipal road, the 40–60 tph range gives the best balance because:

  • The plants are compact and easy to move

  • Fuel consumption stays low

  • Setup time is short

  • Maintenance is simple

  • Investment is reasonable

This range is widely used in Indonesia for local government projects, small contracting companies, and asphalt suppliers who run regional businesses.

ALYT Series mini mobile drum mix plant for sale

So, Is a 40–60 TPH Asphalt Plant Enough?

Based on capacity, daily paving output, scheduling, and hauling conditions, here is the direct conclusion:

  • 40 tph is enough when the daily paving target stays under 300 tons.

  • 60 tph is enough when you need smoother logistics and faster project completion.

For most 50,000 m² municipal jobs, the 60 tph plant offers better performance and more stable project rhythm. But the final decision depends on how fast you want to finish and how your team organizes the paving cycle.

Talk To Me For A Matching Solution

If you want a plant that fits your municipal project, I can help you calculate your daily asphalt demand, hauling distance, and working hours. I also support full setup in Indonesia with local service teams, which many clients prefer because it reduces downtime. Let me know your project scale, timeline, and location. I will recommend the exact asphalt plant configuration—from drying drum to burner and hot mix storage—to help you complete your 50,000 m² road in the most efficient and economical way.